    HOT TAP & VALVE INSERTION – With By-Pass Chilled Water Pipeline

      Location Hong Kong – Infrastructural Network Provider Project Completed May 2023 Technical Details Pipe Material  : Carbon Steel Pipe Size  : DN 400 Medium  : Industrial Water Pressure  : 3.5 Bar (50 psi) Technical Challenges The challenge was to modify an existing pipeline for future expansion with uninterrupted operation. Technical Solutions Hot Tap c/w […]

    More
  • March 30, 2021

    HOT TAPPING ON HIGH PRESSURE NITROGEN PIPELINE

      Location Jurong Island Project Timeline February 2021 Technical Details Pipe Material:   Galvanized Steel SCH40 Pipe Medium:   Nitrogen (N2) Gas Pressure:   30 barg Temperature:   Ambient Pipe Diameter:   DN 250 Coring Diameter:   DN 200 Height of work:   8 metres from ground Technical Challenges An industrial gas supplier engaged Alstern’s […]

    More
Call us at +65 6747 1527

Click for Contact Form

Share your concerns and our consultants will be in touch right away

Open chat
Got a query?
Hi!
We Solve Complex Engineering Challenges. How can we help you?